We’re Hiring! Join the McDonald York Team and be a part of Building the Triangle. View Current Openings
X

BASF Chiller Plant

  • Location: Raleigh, NC
  • Size: 5,900 SF
  • Market: Corporate
  • Client: BASF

Replacement of four existing chillers for three York 750 Ton Chillers, new primary, secondary, condenser pump stations, replacement of two cooling towers, and all associated piping, wiring and controls. This project would not have been possible in today’s supply chain issues without extensive pre-construction planning with the client and vendors. The removal of existing chiller and installation of new chillers was made possible with detailed logistical planning to overcome size and clearance challenges. The design team involvement and diligence also aided in a successful project with the phasing and work sequencing plans. This allowed our client to maintain a fully operational site with only limited periods without redundant systems in place.